ON SITE PROGRESS
Package I:
Civil Works
Including Runway, Taxiway & Apron
& Storm Water Drainage Works
& Fencing & Perimeter Track
& Watch & Ward Tower
Overall Progress of Package I
100 %
Package II:
Airside Electrical Works
Including Electrical Works for Runway, Taxiway & Apron
& Civil Works for Runway Transformer Pits
& Vault Station
Overall Progress of Package II
98.5 %
Package IIIA-1:
Cargo Complex
Including Cargo Building
& Gate House
& Amenities Building
Overall Progress of Package IIIA-1
100 %
Package IIIA-2:
FCR Building & Miscellaneous
Including FCR Building / ATC Tower
MDS Building
Underground Water Tank
Water Tower , Maintenance Office
Overall Progress of Package IIIA-2
100 %
Package IIIA-3:
Internal Road Network , Water Supply & Sewerage Works
Overall Progress of Package IIIA-3
82 %
Package IIIA-4:
External Electrical Works
Overall Progress of Package IIIA-4
97 %
Package-IIIB-I:
Passenger Terminal Building - Structural Work
Overall Progress of Package IIIB-1
99 %
Package-IIIB-2:
International Passenger Terminal
Overall Progress of Package IIIB-2
75 %
Package-IV:
ATC & Navigational Aids
Overall Progress of Package IV
100 %
Calibration of the Navigational Aids
Overall Progress
100 %
Package-V:
Airport Operational Equipment
Overall Progress of Package V
100 %
Package-VI:
Ground Handling Equipment
Overall Progress of Package VI
100 %
Construction of ASF Barracks
Overall Progress
100 %
Leveling & Grading of various areas of the Airport
Overall Progress
93 %
Apron Flood Lighting System
Overall Progress
100 %
SIAL Mosque
Overall Progress
50 %
Air Field Lighting System
Overall Progress
100 %
Passenger Terminal Building (Finishing Work)
Overall Progress
28 %