LATEST PROGRESS REPORT
 
Administration Block
100 %
 
Cargo Terminal
98 %
 
Domestic Terminal
100 %
 
ATC Tower
100 %
 
Runway, Apron and Taxi Way
100 %
 
Air Field Lighting System
100 %
 
GHE Shed
85 %
 
Cargo Truck Parking
98 %
 
FCR building
100 %
 
Ground Handling Equipment
100 %
 
   
 
 