LATEST PROGRESS REPORT
 
Administration Block
100 %
 
Cargo Terminal
98 %
 
Domestic Terminal
92 %
 
ATC Tower
95 %
 
Runway, Apron and Taxi Way
98.5 %
 
Air Field Lighting System
98 %
 
Cargo Truck Parking
98 %
 
FCR building
95 %
 
Ground Handling Equipment
100 %
 
   
 
 